Overview
HMAS Watson base is located on a 14.6 hectare site off Cliff Street at Sydney’s South Head in New South Wales. The HMAS Watson Redevelopment project is addressing functionality and capacity shortfalls in facilities and infrastructure on the base.
The project also aims to address high risk issues associated with non-compliant facilities and reduce ongoing operating costs by consolidating similar functions.
HMAS Watson site images (PDF, 1.11 MB)
Community information
Defence consulted with local residents, statutory authorities and other interested stakeholders as part of obtaining Parliamentary expediency for the works to proceed under the provisions of the Public Works Act 1969. Consultation was conducted during September and October 2019 with a community information session held in 2020.
Defence will conduct further community information sessions throughout the construction phase of the project.
Traffic and parking
Defence commissioned a traffic consultant to assess the traffic impacts of the construction activities. The assessment considered impacts to existing traffic networks including roads, public transport, pedestrian and cycling paths.
HMAS Watson Traffic and Parking Impact (PDF, 412.1 KB)
Noise management
Defence commissioned a specialist environmental consultant to assess the noise impacts of the construction activities on the local community.
Noise management and treatment measures will be implemented to reduce noise where measures may exceed acceptable limits. Treatment measures are designed to ensure any impacts are minimised.
HMAS Watson Noise Impact (PDF, 1.15 MB)
Project details
Planned works for the next 6 weeks 22/12/2024 to 2/02/2025:
- Off Base
- Temporary guard house remains operational.
- Base access back to 2 lanes.
- Training Facility
- Structural works are ongoing.
- Façade works, Internal Services and Fitout Works ongoing. .
- Health Clinic
- Landscaping works ongoing until late-Nov.
- Base Entry
- Civil works are ongoing.
- Landscaping and finishing work ongoing.
- Line marking works are scheduled 19 Dec 24 between 6pm and 6am. These works are subject to appropriate weather conditions and may be rescheduled if necessary.
- Site Wide Services
- Inground services installation works ongoing.
- Out of hours vehicle movements:
- Line marking and roundabout construction works at the Base Entry. Out of hours access to and from site for line marking equipment and delivery trucks.
HMAS Watson 6 Week Look Ahead (PDF, 19.76 KB)
Timeline
Project element | Description | Expected commencement | Expected completion |
---|---|---|---|
Training precinct | Construct a new training precinct | April 2020 | March 2027 |
Base engineering services | Upgrade and refurbish base engineering services, including fire/potable water, communications networks, and civil infrastructure | April 2020 | August 2023 |
Base security | Install new base security systems including construction of new front entry precinct | April 2020 | July 2024 |
Galleys | Refurbish the existing galleys | April 2024 | January 2026 |
Living-in accommodation | Construct new trainee living In accommodation for at least 236 students, plus consequential works | April 2021 | November 2026 |
Car parking | Construct replacement car parking | July 2026 | March 2027 |