The Defence Infrastructure Panel – Environment, Heritage and Estate Engineering (DIP-EHEE) rates are not published.
The rates will only be provided:
- to inform procurement activities where a schedule of rates response has been sought as part of the Request for Proposal. The panel team will validate the Panel rates against those rates submitted at time of tender.
- to validate a variation that has been submitted under an active contract should the variation be on the basis of a schedule of rates.
If seeking a rate to inform the Endorsement to Proceed, the Panel team can provide an average across the relevant Panel category.
If rates are sought as part of a Request for Proposal, a panellist must use the role descriptors and rates agreed at the panel level in their submission.
Note : there is a 3 day turnaround for all requests related to rates and this should be included in the procurement planning.